Codes

CGNC
A new 400 kV double circuit between Creyke Beck and the south Humber area
Type: Develop new circuits
Status: Design/development and consenting
Boundaries: B7aI; B8; B9
Region: North England
Construct a new 400 kV double circuit in Yorkshire to facilitate power transfer requirements across the relevant boundaries. Substation works are required to accommodate the new circuits.
NOA 2021/22 Refresh Recommendation:
HND essential option
CKPC
Power control device along Creyke Beck to Keadby to Killingholme
Type: Control power flow
Status: Strategic Optioneering
Boundaries: B7aI; B8
Region: North England
Install a power control device along the Creyke Beck to Keadby to Killingholme 400 kV overhead line route. This would improve the capability to control the power flows from north to south of the transmission network.
NOA 2021/22 Refresh Recommendation:
HND essential option
CLN2
New circuit across North West England
Type: Develop new circuits
Status: Scoping
Boundaries: B6I;
Region: North England
New circuit across North West England
NOA 2021/22 Refresh Recommendation:
Proceed - Critical
CMN3
New circuit between south east Scotland and North West England
Type: Develop new circuits
Status: Scoping
Boundaries: B6I; B6SPT; B7aI;
Region: North England
New circuit between south east Scotland and North West England
NOA 2021/22 Refresh Recommendation:
Proceed - Maintain
CS05
Commercial solution for Scotland and the north of England - stage 1
Type: ESO-led commercial solutions
Status: Project not started
Boundaries: B6E; B6I; B6F; B6SPT
Region:
This ESO-led commercial solution provides benefit across boundaries B6 in Scotland and the north of England
NOA 2021/22 Refresh Recommendation:
Proceed - Critical
CS06
Commercial solution for Scotland and the north of England - stage 2
Type: ESO-led commercial solutions
Status: Project not started
Boundaries: B6E; B6I; B6F; B6SPT
Region:
This ESO-led commercial solution provides benefit across boundaries B6 in Scotland and the north of England
NOA 2021/22 Refresh Recommendation:
Proceed - Critical
CS07
Commercial solution for East Anglia - stage 1
Type: ESO-led commercial solutions
Status: Project not started
Boundaries: EC5E; EC5I
Region:
This ESO-led commercial solution provides boundary benefit across the East Anglia boundary
NOA 2021/22 Refresh Recommendation:
Proceed - Critical
CS08
Commercial solution for East Anglia - stage 2
Type: ESO-led commercial solutions
Status: Project not started
Boundaries: EC5E; EC5I
Region:
This ESO-led commercial solution provides boundary benefit across the East Anglia boundary
NOA 2021/22 Refresh Recommendation:
Proceed - Critical
CS11
Commercial solution for the north of England - stage 1
Type: ESO-led commercial solutions
Status: Project not started
Boundaries: B7aE; B7aI; B7aF
Region:
This ESO-led commercial solution provides boundary benefit across the north of England
NOA 2021/22 Refresh Recommendation:
Proceed - Critical
CS12
Commercial solution for the north of England - stage 2
Type: ESO-led commercial solutions
Status: Project not started
Boundaries: B7aE; B7aI; B7aF
Region:
This ESO-led commercial solution provides boundary benefit across the north of England
NOA 2021/22 Refresh Recommendation:
Proceed - Critical