GSR032: Facilitate Implementation of the Electricity System Restoration Standard

This Modification is proposing a number of changes to the SQSS to facilitate the direction issued by BEIS in accordance with Special Condition 2.2 of National Grid’s Electricity System Operator’s Transmission Licence. Implementing an Electricity System Restoration Standard (ESRS) which requires 60% of electricity demand to be restored within 24 hours in all regions, and 100% of electricity demand to be restored within 5 days nationally.

Modification status:
Current - Awaiting Implementation
Last updated:
20 March 2024
  • Code Administrator Contact: Milly Lewis - [email protected]
  • Governance Route: Standard Governance
  • Impacts:  High – Transmission Owners and Offshore Transmission Owners
Code modification proposed by:
Sade Adenola

Documents