CMP298: Updating the Statement of Works process to facilitate aggregated assessment of relevant and collectively relevant embedded generation
The current Statement of Works process can be inefficient and time-consuming where there are concurrent multiple applications. Network Operators have for a number of years trialled and refined a more efficient aggregated assessment (widely known as the “Appendix G” process) of Distributed Generators (DG) that have or may have an impact on the National Electricity Transmission System (NETS). CMP298 seeks to introduce this process into the CUSC, which will sit alongside the current Statement of Works process.
Code Administrator Contact: [email protected]
Governance Route: Standard
Impacts: Medium impact on Distribution Network Operators, Transmission Owners, Embedded Generators and ESO
Documents