CM080:Transmission Impact Assessment Process

NOs are obliged not to connect any new single embedded generation where it “may have an impact on the NETS” without undertaking a “Request for a Statement of Works” to NGESO.  This process does not take into account the growing trend of smaller embedded generation connections.

A “Transmission Impact Assessment” process which facilitates an aggregated assessment process mitigates the need to apply to multiple individual connections saving time/admin and making it easier for NGESO to consider the cumulative impact of smaller individual connections.

Modification status: Current - Code Administrator Consultation

Last updated: 28 April 2022

Code Administrator Contact: Sally Musaka - [email protected]

Governance Route: Standard Governance

Impacts: Medium impact on Transmission Owners

Documents

Proposal Documents

Workgroup Meetings and Summary Papers

Sorry, no documents found.

Workgroup Consultation

Sorry, no documents found.

Workgroup Report

Sorry, no documents found.

Draft/Final Modification Report

Sorry, no documents found.

Decision

Sorry, no documents found.