CMP376 'Inclusion of Queue Management process within the CUSC'

This CUSC modification is to implement the queue management process in to CUSC including introducing a right for the Electricity System Operator (ESO) to terminate contracted projects which are not progressing against agreed milestones.

Modification status: Current - Proposal Raised

Last updated: 28 October 2021

Code Administrator Contact: Paul Mullen – [email protected]

Governance Route: Standard Governance, straight to Code Administrator Consultation#

Impacts: High impact on the ESO; Onshore/Offshore Transmission Owners; Distribution Network Operators and all Users wanting to utilise or connect to the National Electricity Transmission System (NETS)