CMP338: Impact of DNO Contributions on Actual Project Costs and Expansion Factors – New Definition of "Cost Adjustment"

This modification seeks to implement that decision through the addition of the definition of the contribution from a Distribution Network Operator (DNO) as a “Cost Adjustment” as is required by the proposed modification of CUSC 14.15.75 and 14.15.76 as set out in the accompanying CUSC mod CMP337. This modification should be considered in conjunction with CUSC mod CMP337 - both CUSC modifications should be progressed and approved simultaneously.

Modification status:
Current - Pending Implementation
Last updated:
20 March 2024

Code Administrator Contact: Paul J Mullen - [email protected]

Governance Route: Standard Governance - Urgent 

Implementation Date: 01 April 2024

Impacts:

* Medium: Distribution Network Operators, Transmission Owners, Remote Island Generators (Shetland, Western Isles and Orkney)

* Low: ESO, all Users who pay Generation TNUoS

Code modification proposed by:
Michael Ferguson