CMP330: Allowing new Transmission Connected parties to build Connection Assets greater than 2km in length & CMP374: 'Extending contestability for Transmission Connections'

CMP330: To amend the definition of Connection Assets in section 14 of the CUSC to allow cable and overhead line lengths over 2km to be contestable where agreed between the Transmission Owner and the User.

CMP374: To allow new connectees to construct transmission assets to facilitate their connection to the wider transmission network.

Modification status: Current - Workgroup Stage

Last updated: 29 September 2021

Code Administrator Contact: Paul J Mullen [email protected] 

Governance Route: Standard 

Impacts:

* Medium: New Transmission connected sites; Transmission Owners