CMP265: Gross charging of TNUoS for HH demand where embedded generation is in Capacity Market

CMP265 specifically seeks to address the issue that half hourly metered (HH) demand for TNUoS purposes is currently charged net of embedded generation. CMP265 has been proposed as urgent, we are awaiting a decision from Ofgem on this.

Modification status:
Concluded - CMP265: Gross charging of TNUoS for HH demand where embedded generation is in Capacity Market
Last updated:
20 March 2024

Code Administrator Contact: Caroline Wright - [email protected]

Governance Route: Standard 

Impacts:

* High: Suppliers and embedded generators

Implemented: 01 April 2018

Documents