CMP213: Project TransmiT TNUoS Developments

This proposal seeks to modify the CUSC so that the TNUoS charging methodology recognises that the impact on incremental transmission network cost varies for generators with different characteristics as well as location; that HVDC circuits that parallel the main transmission network are represented within the charging methodology; and to extend the charging methodology to include island transmission connections comprised of sub-sea cable technology.

Modification status:
Concluded - CMP213: Project TransmiT TNUoS Developments
Last updated:
20 March 2024

Code Administrator Contact:  Jackeline CrespoSandoval - jackeline.cresposandoval@ nationalgrid.com 

Governance Route: 

Impacts: Standard 

* Low: All other CUSC parties liable for TNUoS charges

Implemented: 01 April 2016