Frequency Risk and Control Report (FRCR)

The Frequency Risk and Control Report includes an assessment of the magnitude, duration and likelihood of transient frequency deviations, forecast impact and the cost of securing the system and confirms which risks will or will not be secured operationally.

The requirement for a Frequency Risk and Control Report was introduced following the approval of Security and Quality of Supply Standards (SQSS) modification GSR027. The first version of the report was submitted to Ofgem on 1st April 2021 and approved on 12th May 2021.

The FRCR is produced at least once annually and is consulted on with industry and reviewed by the SQSS Panel ahead of submission to Ofgem.

The 2022 FRCR methodology and FRCR is being consulted between 21st  February 2022 and 4th March 2022. It will concentrate on simultaneous events and be submitted to Ofgem for approval on 1st April 2022.

For more information please contact [email protected].