GC0104: EU Connection Codes GB Implementation – Demand Connection Code

Modification status: Current

Last updated: 25 September 2018

This modification was raised by:

National Grid in August 2017

Purpose of Modification:

This modification will set out within the Grid Code new compliance obligations as specified in the Demand Connection Code (DCC):

  1. Technical requirements for new* Transmission-connected Demand Facilities; Transmission-connected Distribution Facilities and Distribution Systems.
  2. Technical requirements for Demand Units used by a Demand Facility or a Closed Distribution System to provide Demand Response Services to System Operators.

* ‘New’ is defined as not being connected to the system at the time that the code enters into force and not having concluded a final and binding contract for the purchase of main plant items by two years after entry into force.

The governance route for this modification is:

Standard

The impact of this modification is on:

Transmission System Operators (TSOs), Transmission Connected Demand Facilities, Demand Facilities providing DSR, Aggregators and Directly Connected Transmission Facilities; Distribution Network Operators and Operators of Demand schemes considering modernisation

The modification is currently at:

Pending Implementation

Documents

Authority Decision