Super SEL

Super SEL is utilised to directly decrease the sum of the minimum MW level or Stable Export Limit (SEL) of generators synchronized to the system by lowering the minimum generating level at a generator synchronised.

Super SEL providers must:

  • Deliver a minimum of 10MW of Footroom
  • A maximum notice period of 12 hours before SEL reduction

Please see the interactive guidance document for further details.